I have a project that I scheduled to run every 11th of the month, but it’s not triggered when the set time passes. However, if I change the scheduling to weekly and I select Monday, it’s triggered just fine. I thought maybe it was a date format issue (my region uses 31-12-2021, not 12-31-2021), but choosing the 4th instead of the 11th didn’t change a thing. This project has also been scheduled since february, so I don’t think the problem can be that the date on the server is somehow out of sync. Please help!
Hi Ruben,
What is your Server version?
See also:
It’s 5.1.2.1, so it should be fixed if I get it updated. Thanks!